Control Room Stanwell, Mica Creek Scope: - Review current instrument and electrical requirements to relocate a control room. - Assess risks. - Scope control system upgrade requirements. - Develop a cutover plan for a running power station. - Determine budgets. Safety: - Zero Lost Time Injuries. - Zero Medical Treatment Injuries. Completion: March 2020.

Control Room

Stanwell, Mica Creek

Scope:
– Review current instrument and electrical requirements to relocate a control room.
– Assess risks.
– Scope control system upgrade requirements.
– Develop a cutover plan for a running power station.
– Determine budgets.

Safety:
– Zero Lost Time Injuries.
– Zero Medical Treatment Injuries.

Completion:
March 2020.