Power Station GPS Synchronized Timecode

GPS time synchronization receiver installed and connected to the Plant Wide control system Stanwell: Far North Queensland power station Scope: - Design and issue drawings. - Procure equipment, stage and test. - Design lightning protection circuits and select equipment. - Complete a site installation and quality plan. - Install GPS receiver and lightning arrestors on site, run cabling to Plant Wide control system. - Configure software in control system to synchronize time automatically. - Test and hand over Safety: - Zero Lost Time Injuries. - Zero Medical Treatment Injuries. Completion: March 2016.

GPS time synchronization receiver installed and connected to the Plant Wide control system

Stanwell: Far North Queensland power station

Scope:
– Design and issue drawings.
– Procure equipment, stage and test.
– Design lightning protection circuits and select equipment.
– Complete a site installation and quality plan.
– Install GPS receiver and lightning arrestors on site, run cabling to Plant Wide control system.
– Configure software in control system to synchronize time automatically.
– Test and hand over

Safety:
– Zero Lost Time Injuries.
– Zero Medical Treatment Injuries.

Completion:
March 2016.